Project: Winster Sub – Energy

  • 13th October 2011 – 10.30am – ScrewFast Commercial Manager receives call from Siemens – Winster Substation in Derby has exploded!
  • Require 10 No. 114 helical piles to support switchboard container.
  • 14th October 2011 – 5.30am – Materials and excavator collected and on site by 8.30am.
  • All successfully installed 5 hours later!