Project: Redcar- Environmental

  •  Birse were awarded a £21M contract to reduce the flood risk to
    1000 properties.
  •  The flood defences stretch for 2.7km reducing erosion &
    flood risk for at least 50 years.
  •  Installed section by section to reduce disruption to residents
    and visitors, 132 helical piles were installed across 3 zones
    in just 5 weeks;
  • Zone 1 = 59 piles @ 11.5m long; Zone 2 = 63 piles @ 10.5m long;
    Zone 3 = 10 piles @ 9m long.